# AWS sells 75% of 13 data centre buildings to Blackstone's REIT for about $5B and leases them back. What the terms show

> Blackstone Digital Infrastructure Trust is buying majority control of 13 new AWS "powered shell" buildings at a 7% cap rate, with AWS renting all of them back for 12 to 32 years. It shows one way hyperscalers can pay for the AI build-out without owning every building.

Published Nov 16, 2026 by TechMeasured Staff · Business · Canonical: https://techmeasured.com/business/aws-sells-75-percent-13-data-centers-blackstone-5-billion-leaseback-what-terms-show

Blackstone Digital Infrastructure Trust (NYSE: BXDC) has agreed to buy a **75% stake** in two joint ventures that own **13 newly built data centre buildings** on two Amazon Web Services campuses. The deal values the portfolio at about **$5 billion**. AWS keeps the other 25% and will lease back **all 13 buildings**. The terms are in BXDC's [November 16 press release](https://www.sec.gov/Archives/edgar/data/0002100161/000119312526461954/d115778dex991.htm), filed with the SEC. Closing is expected in the fourth quarter, subject to the usual conditions.

Why it matters: AI data centres need huge amounts of money up front. In a sale-leaseback, a hyperscaler sells most of a building it has already finished, keeps using it on a long lease, and gets back money to spend on the next one. Investors get long-term rent from one of the strongest tenants in tech. For BXDC, which [The Next Web](https://thenextweb.com/news/blackstone-bxdc-aws-data-centres-5bn) says listed in May, this is its first acquisition.

## The terms

| Item | Detail |
|---|---|
| Buyer | Blackstone Digital Infrastructure Trust (BXDC) |
| Stake bought | 75% of two joint ventures; AWS keeps 25% |
| Assets | 13 newly built "powered shells" on two AWS campuses |
| Approximate value | $5 billion |
| Lease | AWS rents 100% of the buildings, triple-net |
| Lease term | 12 years initially, up to 32 with extensions |
| Initial cap rate | 7.0% |
| Expected close | Q4 2026 |

Source: BXDC press release. The campuses, their locations and their power capacity in megawatts are **not disclosed**. Neither are rent escalators. None of the four outlets we read gives those figures. Some newsletters have circulated megawatt and escalator numbers, but we couldn't trace them to a filing, so we've left them out.

## What the jargon means

- **Powered shell.** The building, with a utility power connection, but not the servers, chips or usually much of the fit-out. BXDC is buying real estate and power hookups, not AWS's computing equipment.
- **Triple-net.** AWS, as tenant, pays property taxes, insurance and maintenance. BXDC's income is close to pure rent.
- **7% cap rate.** First-year net operating income divided by the price. On $5 billion, Yahoo Finance's GuruFocus write-up puts that at about **$350 million** a year. [WRE News](https://wrenews.com/blackstone-amazon-data-centers-5-billion-sale-leaseback-november-2026/) points out that this is a pricing benchmark for one deal, not a valuation for all data centres.

For context, WRE News lists the 10-year Treasury yield at **5.10%** on November 12. A 7% initial yield is therefore roughly two points above the 10-year Treasury, for a lease that can run for decades.

## Who pays for it

The press release doesn't say how BXDC will fund the deal. Its CEO, Nick Pell, calls it a deployment of the trust's IPO proceeds. According to the [Yahoo Finance/GuruFocus report](https://finance.yahoo.com/markets/stocks/articles/amazon-stocks-fall-2-56-192513974.html), which cites Finimize, Blackstone plans to use about **$1.9 billion** of IPO money and about **$2.5 billion** of non-recourse mortgages. We have not seen those figures in a filing.

AWS frames the deal around its expansion plans. Its VP of infrastructure, Prasad Kalyanaraman, says in the release that the partnership lets AWS "continue expanding responsibly."

## Market reaction, and what it doesn't tell you

Amazon shares were down **2.56%** at 10:10 a.m. ET on November 16, according to the GuruFocus report. But the same page's market ticker showed the Nasdaq down about 2.5% and BXDC up about 4.6%. On a day when tech stocks fell broadly, it's hard to put Amazon's drop down to this deal. TNW notes that BXDC also reported third-quarter results the same day: net income of **$15.6 million**, or $0.15 a share, up from $7.1 million in the second quarter.

## Why it's worth watching

- **A template.** If other cloud and AI companies copy this structure, more of the AI build-out will sit on real-estate investors' balance sheets, with the tech companies as long-term tenants.
- **Lease risk sits with the landlord.** AWS has committed to only 12 years, with options to extend to 32. If demand for these campuses fell, the extensions are where the landlord would feel it.
- **Disclosure gaps.** BXDC hasn't named the campuses or given their power capacity. Watch its closing announcement and next quarterly filing for those details, and for the actual financing mix.


## Sources

1. [SEC — Blackstone Digital Infrastructure Trust Form 8-K, Exhibit 99.1 (press release, Nov 16, 2026)](https://www.sec.gov/Archives/edgar/data/0002100161/000119312526461954/d115778dex991.htm)
2. [The Next Web — Blackstone's data centre trust buys 75% of 13 AWS buildings in $5bn deal](https://thenextweb.com/news/blackstone-bxdc-aws-data-centres-5bn)
3. [Yahoo Finance (GuruFocus) — Amazon Stocks Fall 2.56% as AWS Sells Data Center Control in $5 Billion Deal](https://finance.yahoo.com/markets/stocks/articles/amazon-stocks-fall-2-56-192513974.html)
4. [WRE News — Blackstone, Amazon Agree to $5B Data Center Deal](https://wrenews.com/blackstone-amazon-data-centers-5-billion-sale-leaseback-november-2026/)